Extension of the institutional strengthening project (phase IV)

The Ozone Unit will coordinate the implementation of all phase out activities of the country programme and the RMP update including reinforcement of ODS regulations by putting in place a quota system to gradually limit the quantities of ODS imported into the country; providing more training for refrigeration technicians; public awareness activities; monitoring the 1st phase of the RMP and developing activities for an update of the RMP; and reporting progress to the Fund Secretariat and Article 7 data to the Ozone Secretariat.
 
Country: Comoros
Network: AFR French
Project Type: Institutional strengthening
Sector: Several
Sub-sector: Ozone unit support
Approval / start date: 4/1/2005
Status: Completed
Project Category: Multilateral Fund
UNEP Office: ROA

 